Construction Updates

On-site construction began in May 2020 and will take approximately 24 months to complete. At that time, some work will remain, including the removal of the existing Hawkins Point and Sollers Point terminal stations.

Throughout the construction of the Key Crossing Reliability Initiative project, BGE will regularly provide updates on project progress:

On-site construction activities week of 12/15/2021

  • Installing formwork at Tower 3 and Tower 4 vessel collision protection structures
  • Installing topping rebar at Tower 3 and Tower 4 vessel collision protection structures
  • Installing fender system for Tower 5 vessel collision protection structure
  • Performing pile coating repairs at Tower 3 vessel collision protection structure
  • Performing ladder installations at Tower 1, Tower 4, and Tower 7
  • Mobilizing barges in water and relocating as needed to get work completed


On-site construction activities week of 12/8/2021

  • Installing formwork at Tower 3 and Tower 4 vessel collision protection structures
  • Installing topping rebar at Tower 4 vessel collision protection structure
  • Performing cathodic protection and grounding on Tower 4 vessel collision protection structure
  • Installing fender system for Tower 5 vessel collision protection structure
  • Performing pile coating repairs at Tower 3 vessel collision protection structure
  • Installing marker balls between Tower 1 and Tower 2
  • Clipping in new conductor and installing conductor spacers and dampers
  • Mobilizing barges in water and relocating as needed to get work completed


On-site construction activities week of 12/1/2021

  • Installing formwork at Tower 3 and Tower 4 vessel collision protection structures
  • Installing topping rebar at Tower 4 vessel collision protection structure
  • Performing cathodic protection and grounding on Tower 3 vessel collision protection structure
  • Installing fender system for Tower 5 vessel collision protection structure
  • Performing pile coating repairs at Tower 3 vessel collision protection structure
  • Mobilizing barges in water and relocating as needed to get work completed